Tender process for Saudi Arabia WWTPs - 2018

ClientAlmar Water
TypeConsultancy

Supporting services for the development of tender documents for various tender processes in the Kingdom of Saudi Arabia.
Complete developmet of Asset Management and Risk Management plans.

Tender process for Saudi Arabia WWTPs - 2018

Closeout of the Waste Water Treatment Plant and Sewage Network Project in the city of Berane (Montenegro) - 2018

ClientFCC Aqualia
TypeProject Management - Interim Management

Budget: € 11 Million

Total lenght of sewage pipes: 20 km
Compact Pretreatment and Sequential Batch Reactor (SBR)
Q med = 190 m3/hour
20.000 EH

Allocation of a Project Manager accounting over 25 years of experience for a period of 8 months to carry out the final works and the closeout of the Construction phase of the Project.

Closeout of the Waste Water Treatment Plant and Sewage Network Project in the city of Berane (Montenegro) - 2018

Contract Management support for three Waste Water Treatment Plants in the cities of Pljevlja, Berane and Prizren (Balkans) - 2018

ClientFCC Aqualia
TypeConsultancy
FIDIC Red and Yellow type of Contracts

Follow-up of the Projects' development.
Punctual visits to the Sites.
Monitoring and control of contractual issues.
Tracking of variations and claims.
Drafting of communications to the Engineer and the Client.
Contract Management support for three Waste Water Treatment Plants in the cities of Pljevlja, Berane and Prizren (Balkans) - 2018

Issuance of Technical Reports and Forensic 2018-2019

ClientTORRESCAMARA
TypeForensic
Support for the issuance of Technical and Expert Reports.
Issuance of Technical Reports and Forensic 2018-2019

Critical Path analysis - 2018

ClientKPMG
TypeForensic
Budget: €5 Million

Project Schedule and Critical Path Analysis for SEMI's "Contract for the Turnkey Project of the 225kv line from Centrale duale to OMVS (Nouakchott) and its electric substations" in Mauritania.
Critical Path analysis - 2018

Issuance of Expert Reports / Forensic 2019-2020

ClientRover Infraestructuras
TypeForensic
Issuance of Expert Reports / Forensic from 2019 to nowadays.
Issuance of Expert Reports / Forensic 2019-2020

Commissioning of the Berane Waste Water Treatment Plant (Montenegro) - 2019

ClientFCC Aqualia
TypeProject Management - Interim Management
Compact Pretreatment and Sequential Batch Reactor (SBR)
Q med = 190 m3/hour
20.000 EH

Allocation of a Commissioning Manager accounting 30 years of experience in similar projects for a period of 4 months.
Development of a detailed Work Programm, management of suppliers and subcontractors, and fluent communication and reporting to Aqualia.
Frequent issuance of follow-up reports.
Development of Commissioning Manual and Takeover documents for Client's acceptance.
Commissioning of the Berane Waste Water Treatment Plant (Montenegro) - 2019

Closeout of the Waste Water Treatment Plant Project in the city of Prizren (Kosovo) - 2019

ClientFCC Aqualia
TypeProject Management - Interim Management

Budget: €10 Million

Pretreatment, primary settlers, trickling filters, secondary clarifiers
Q med = 533 m3/hour
50.000 EH

Allocation of a Project Manager accounting over 25 years of experience and a Construction Manager with more than 10 years of experience to carry out the final works and the closeout of the Construction of the Project.

Closeout of the Waste Water Treatment Plant Project in the city of Prizren (Kosovo) - 2019

Commissioning of the Prizren Waste Water Treatment Plant (Kosovo) - 2020

ClientFCC Aqualia
TypeProject Management - Interim Management
Pretreatment, primary settlers, trickling filters, secondary clarifiers
Q med = 533 m3/hour 
50.000 EH

Allocation of a Commissioning Manager accounting 30 years of experience in similar projects for a period of 6 months.
Development of a detailed Work Programm, management of suppliers and subcontractors, and fluent communication and reporting to Aqualia.
Frequent issuance of follow-up reports.
Development of Commissioning Manual and Takeover documents for Client's acceptance.
Commissioning of the Prizren Waste Water Treatment Plant (Kosovo) - 2020